BEPCⅡ: construction and commissioning

Get Citation
ZHANG Chuang. BEPCⅡ: construction and commissioning[J]. Chinese Physics C, 2009, 33(S2): 60-64. doi: 10.1088/1674-1137/33/S2/016
ZHANG Chuang. BEPCⅡ: construction and commissioning[J]. Chinese Physics C, 2009, 33(S2): 60-64.  doi: 10.1088/1674-1137/33/S2/016 shu
Milestone
Received: 2009-01-06
Revised: 1900-01-01
Article Metric

Article Views(3956)
PDF Downloads(567)
Cited by(0)
Policy on re-use
To reuse of subscription content published by CPC, the users need to request permission from CPC, unless the content was published under an Open Access license which automatically permits that type of reuse.
通讯作者: 陈斌, bchen63@163.com
  • 1. 

    沈阳化工大学材料科学与工程学院 沈阳 110142

  1. 本站搜索
  2. 百度学术搜索
  3. 万方数据库搜索
  4. CNKI搜索

Email This Article

Title:
Email:

BEPCⅡ: construction and commissioning

    Corresponding author: ZHANG Chuang,
  • Institute of High Energy Physics, CAS, Beijing 100049, China

Abstract: 

This is a status report of the project on befalf of the BEPCⅡ team. BEPCⅡ is a major upgrade of the BEPC (Beijing Electron-Positron Collider). It is a double-ring e+-e collider as well as a synchrotron radiation (SR) source with its outer ring, or SR ring. As a collider, BEPCⅡ operates in the beam energy region of 1—2.3 GeV with design luminosity of 1×1033 cm-2s-1 at 1.89 GeV. As a light source, the SR ring operates at 2.5 GeV and 250 mA. Construction of the project started in the beginning of 2004. Installation of the storage ring components was completed in October 2007. Commissioning is in progress. There are still many issues for further studies before reach to 3×1032 cm-2s-1.